P6 Schedule Analytics & Forensics
Drop in a Primavera .xer or .xml export and get the whole progress picture in seconds — no P6 licence needed. It recomputes the critical path on the file's own calendars, so it shows where the stored float disagrees with the logic.
- Earned value & earned schedule — SPI(t), SV(t), forecast finish
- DCMA 14-point assessment with drill-down to each offending activity
- NEC4 clause 31 & 32 compliance checks for programme submission
- Monte Carlo QSRA, windows delay analysis and trend across updates
- XER repair — fix logic defects and write a corrected file, every change reviewed first
The demo runs a sample fit-out project, analysed by the real engine. No client data.
The dashboard — earned value, earned schedule and forecast finish, with the S-curve below.